RPC Completes Successful Hydrostatic Testing for Tambak Lorok – 28/2/2019

RPC Completes Successful Hydrostatic Testing for Tambak Lorok – 28/2/2019

Indonesia:This week, RPC successfully completed Stage 1 Hydrostatic testing of 2.4m Diameter GRP cooling water pipe for the Tambak Lorok Combined Cycle Power Plant Block 3 Project for Indonesia Power (IP). The plant will commence operation in mid-2020 and add 780 MW of electricity to the Indonesia grid, equivalent to supplying five million homes. The