RPC Completes Successful Hydrostatic Testing for Tambak Lorok – 28/2/2019 | RPC Technologies
17630
post-template-default,single,single-post,postid-17630,single-format-standard,bridge-core-1.0.4,ajax_fade,page_not_loaded,,qode_grid_1300,qode-theme-ver-18.1,qode-theme-bridge,qode_header_in_grid,wpb-js-composer js-comp-ver-6.0.3,vc_responsive

RPC Completes Successful Hydrostatic Testing for Tambak Lorok – 28/2/2019

RPC Completes Successful Hydrostatic Testing for Tambak Lorok – 28/2/2019

Indonesia:This week, RPC successfully completed Stage 1 Hydrostatic testing of 2.4m Diameter GRP cooling water pipe for the Tambak Lorok Combined Cycle Power Plant Block 3 Project for Indonesia Power (IP). The plant will commence operation in mid-2020 and add 780 MW of electricity to the Indonesia grid, equivalent to supplying five million homes. The